Project Profile
Project Name :

Pre-commissioning of 12”/16”/24’’ gas line

Duration :

3 months

Client :

Moody International

Work Volume :

16 KM.

Project Description :

Execute the hydrostatic tests and the pre-commissioning activities according to the required specs and the following scope of work:
1. Initial cleaning andPurging.
2. Water filling and venting.
3. Hydrostatic testing.
4. Bulk dewatering.
5. Final dewatering.
6. Final cleaning and initial drying (for complete pipeline length)
7. Final drying.
8. Nitrogen purging and packing to 1 bar (including supplying nitrogen)
9. Pneumatic air leak test before and after the hydrostatic test
10. Supplying all needed cleaning and gauging pigs required
11. Supplying water and water drainage.
12. Loading and unloading.

Project Name :

Pre-commissioning of 8″, gas line

Duration :

2 months

Client :

Moody International

Work Volume :

10 Km

Project Description :

Execute the hydrostatic tests and the pre-commissioning activities according to the required specs and the following scope of work:
1. Initial Cleaning and Purging
2. Water Filling and Venting
3. Air Leak Test
4. Hydrostatic Testing
5. Bulk Dewatering
6. Air Leak Test
7. Final Dewatering.
8. Final Cleaning and Initial Drying (for complete pipeline length)
9. Final Drying
10. Nitrogen Purging and Packing to 1 bar (Including Supplying Nitrogen)
11. Supplying all needed cleaning and gauging pigs required

Project Name :

TE/ENPPI – GPC Project

Duration :

10 months

Client :

Thermoengineering.

Project Description :

Elevated flare package supply, fabrication & Painting.

Project Name :

Delta Dyeing Water Discharge Network

Duration :

5 months

Client :

MAS Engineering

Project Description :

Supply, Fabrication, and Erection& Testing of drainage network

Project Name :

Hydraulic Lifting Car Parking Machine

Duration :

26 months

Client :

Elite

Project Description :

Sheet metal & steel structure fabrication work.

Project Name :

ELNG Plant Idku

Duration :

1 month

Client :

ELNG

Work Volume :

240,000Mhrs

Project Description :

Supply, Fabrication & Installation of black steel. A-Frame

Project Name :

Middle East Oil Refinery (Midor)

Duration :

7 months

Client :

Dailm

Work Volume :

240,000Mhrs

Project Description :

Steam tracing and erection of two compressor unit including piping works.

Project Name :

Naphtha Isomerization Plant

Duration :

5 months

Client :

LurgiResta

Work Volume :

150,000Mhrs

Project Name :

Gas Pipe Lines Network

Duration :

15 months

Client :

ESACO

Work Volume :

120,000Mhrs

Project Name :

Chlorine Liquefaction Plant

Duration :

11 months

Client :

Technifrigo

Work Volume :

200,000Mhrs

Project Description :

Mechanical works.

©2012 C.S.I All rights reserved.