Scope of work:
- Electromechanical installation Works & 26” export gas pipeline, the contracted work consists of the following:
- Mechanical works.
- Electrical works.
- Instruments installation works.
- Insulation works.
- Painting works.
- Pre-commissioning activity.
- Works for the export gas pipeline from compressing station to sea line, including civil works, unpaved service road, grading of right way and pipeline installation.
- Works for the 26” interconnecting pipeline between GASCO facilities and EMG compressing station length about 210 m, (civil works and installation).